- Project included the design and construction of a new 1,000,000 gallon concrete storage tank with custom floor to service 24-inch diameter inlet/discharge piping, 200 HP electric and 150 HP diesel engine centrifugal self-priming, suction-lift wastewater pumps, a control building and an access stair and operations platform located in Santa Rosa Beach, Florida. Facility was designed to accommodate six (6) future 200 HP pumps, a screening and grit removal system, an additional high capacity sewer lift station and emergency power.
- Project responsibilities included, but were not limited to:
- Detailed engineering and design
- Regulatory permitting
- Development of project specifications and bid packages
- Solicitation of material and construction bids
- Review contractor and material supplier pre-qualifications and award contracts
- Construction supervision/management, inspection and certification
- Project Summary:
- Site clearing, grading and testing
- 100,000 gallon concrete process tank
- Two (2) 200 HP electric and one (1) 150 HP diesel engine centrifugal self-priming, suction-lift wastewater pumps
- 10,000 linear feet of 24-inch (24”) PVC sewer forcemain
- 1,000 linear feet of 30-inch (30”) HDPE directional bore pipe
- Twelve (12) 24-inch (24”) gate valves
- Aluminum access stairs and operations platform
- Integrated system control and data acquisition (SCADA)
- Control building (rated at 140 MPH)
- System integration
- Engineering Schedule: 8 weeks
- Construction Schedule: 16 weeks
Approximate Project Cost: $2,000,000
Back to Civil Portfolio