- Project included the design and construction of a new 730,000 gallon aerobic digester, complete with concrete storage tank, air diffuser system, 200 HP blowers, sludge transfer pump system and access platform located in Pont Washington, Florida.
- Project responsibilities included, but were not limited to:
- Detailed engineering and design
- Regulatory permitting
- Development of project specifications and bid packages
- Solicitation of material and construction bids
- Review contractor and material supplier pre-qualifications and award contracts
- Construction supervision/management, inspection and certification
- Project Summary:
- Site grading and testing
- Two (2) new 15 horsepower sludge transfer pumps
- Sludge transfer piping and valves
- 730,000 gallon concrete process tank
- Demolition and re-purposing of existing steel sludge transfer piping
- 1,200 linear feet of new 8-inch (8”) steel transfer piping
- Aluminum access stairs and operations platform
- Two (2) 200 HP blowers and integrated controls
- Blower building (rated at 140 MPH)
- Coarse air diffuser system and air piping
- System process and control integration
- Engineering Schedule: 8 weeks
- Construction Schedule: 12 weeks
- Approximate Project Cost: $1,200,000