Land Development and Site Design
Turning a parcel into a buildable site. Grading, layout, utility routing, and a drawing set a reviewer can approve.
- Site and grading plans
- Utility layout
- Construction details
- Quantity basis for bidding
WaterColor, FL
The work
Site, utility, and stormwater design for a 7,200 sq. ft. restaurant and office building.
Infrastructure design included paved areas such as roadways, sidewalks and parking, potable water and sanitary sewer utilities and a stormwater drainage and management system. Permitting included a Walton County Minor Development Order, Northwest Florida Water Management District (NWFWMD) Environmental Resource Permit (ERP), Florida Department of Environmental Protection (FDEP) Water Distribution Permit, and a FDEP Wastewater Collection Permit.
Each line below is a discipline our staff carried on this project. The description explains what that work involves and what the owner receives at the end of it.
Turning a parcel into a buildable site. Grading, layout, utility routing, and a drawing set a reviewer can approve.
The gravity and lateral system for a new building, designed to the current Florida Building Code and the wind exposure the site sits in.
Work in WaterColor follows the same sequence at any size. Owners see the same four stages.
We ask what prompted the call, what documents already exist, and what deadline is driving the schedule. If the work does not need an engineer, we say so.
A licensed engineer or a staff member working under one goes to the site, documents conditions, and reviews the drawings and reports already on file.
Findings, drawings, and specifications go out under seal, written so a board can read them and a contractor can bid from them.
During construction we review submittals, answer requests for information, perform Construction Observations, and review pay applications against work in place.
Questions about a similar building? Call the office nearest the site or send the address and the scope, and the discipline lead who owns that work will answer. Compare the Civil Engineering scopes we carry.
The scope page behind the WaterColor Crossings engagement.
The scope page behind the WaterColor Crossings engagement.
President / Principal Engineer
Civil Engineering Manager
Senior Civil Engineer